Typical Project Descriptions
The following table describes common
attributes of transportation impacts for each track, at each POP
Level.
This allows the user to refine decisions about
the most appropriate POP Level for a transportation impact. For
example, a District Project Manager answered the construction
worksheet questions to the best of her knowledge for an upcoming
road widening project, and landed on a POP Score of 2.5. The
worksheet automatically rounded up to a POP Level 3 but after
reading the typical project description, the project manager feels
like her project is less complicated and this description does not
exactly fit. Because her POP Score fell almost half-way between a 2
and 3, she reads the POP Level 2 description and discovers that this
more accurately describes her project and proceeds with a Level 2
recommendation.
While simple categorization of outreach
need provides
the benefit of being able to plan for and better manage multiple
projects, project managers and teams should remember that public
involvement and outreach is a dynamic process. Adjustments are often
required over the life cycle of a project, with corresponding
changes in approach, strategy and tasks. Given this, be aware that a
project may move from level to level on the chart as it evolves from
phase to phase, or even within a single project phase. You can never
complete the POP questions too often. If it feels like your
project
has grown less or more complicated, re-answer the questions and
see
where you come out.
1. Select Appropriate Track
2. Answer Questions and get POP Score
3. Save POP worksheet
4. See POP Project Descriptions
5. Review POP Reference Guide and Outreach
Tools
6. Fill out and save POP Reference Guide
and Workbook
POP Level
Score
Typical Project Description
Level
1
0 - 1
The likelihood of political scrutiny is low, and few
stakeholders/groups must be coordinated with.
The project/effort is likely to be brief in duration and
confined to a smaller area. The public is likely to have little
interest or be supportive of the proposed project/plan, with
little likelihood of controversy. Few if any direct impacts are
expected to adjacent properties and the public. If this is being
driven by the National Environmental Policy Act (NEPA) this
would likely be a Categorical Exclusion (CatEx).
Level
2
1.1 - 2
The likelihood of political scrutiny is low, and few
stakeholders/groups must be coordinated with.
The project/outreach area is likely to be confined to a single
neighborhood or section of the City. The project is either brief
in duration with minor impacts to the public and adjacent
property owners, or is more lengthy in duration but with little
to no impact. Historically, public interest is either low, or
the public has been supportive of similar projects. Care should
be taken to reinforce the positive relationships that exist with
various stakeholder groups. If this is being driven by the
National Environmental Policy Act (NEPA) this would likely be a
Categorical Exclusion (CatEx).
Level
3
2.1 - 3
Political considerations are moderate, and the number of
stakeholders/groups requiring coordination begins to rise in
this level.
The project may span more than one section of the City and
require more intense stakeholder coordination. For construction
projects this is likely to last an entire construction season
with moderate impacts to the public and adjacent stakeholders.
Given the longer project duration and the rising level of
impact, potential for controversy also begins to rise. Public
interest levels also increase, as well as the likelihood for
political or project detractors. If this is being driven by the
National Environmental Policy Act (NEPA) this would likely be a
CatEx or Environmental Assessment (EA).
Level
4
3.1 - 4
There is a high level of anticipated
political interest and multiple stakeholders, groups and
organizations may require coordination by and with the
project team.
The project/plan scope likely covers multiple neighborhoods and
a larger geographic region or is a city-wide effort or plan. For
public works, utility or construction projects, the project is
likely to last one to two construction seasons and present
significant delay and impact to the public. The number of
adjacent property impacts is significant or the impacts to a
lesser number of adjacent properties are more severe at this
level. Given the above factors, the likelihood of controversy is
high and the public interest may be high and may be primarily
negative. If this is being driven by the National Environmental
Policy Act (NEPA) this would likely be an EA.
Level
5
4.1 - 5
Political implications associated with this study or
project are considerable, with policy-level decision
makers taking personal interest in project
outcomes.
Corresponding agency interest is also high, with many
government, agencies and special interest groups needing
coordination and involvement. The project scope is large,
with an extensive project or study area, and duration is
likely to span years rather than months. Impacts may be
heavy and of a long duration, ranging from extensive
right-of-way acquisitions to severe lane restrictions and
delay. Again, the likelihood for controversy is high, given
the high stakeholder interest and potential for negative
Department perceptions. If this is being driven by the
National Environmental Policy Act (NEPA) this would likely
be an EIS.